BENECO Power Interruption Schedule
Benguet News

Baguio and Benguet BENECO Power Interruption Schedule for February 15-20, 2021






Several areas in Baguio City and Benguet will be affected by the scheduled Electric Service Interruption of Benguet Electric Cooperative, Inc., (BENECO) from February 15-20, 2021. Sharing with you the following BENECO Power interruption schedule for February 15-20, 2021 to help you prepare if you are affected by the power interruption. Charge your power banks or plan your day because it is going to be an 8-hour brownout for the affected areas. 





BENECO Power Interruption Schedule 

These are the following areas in Baguio City and Benguet affected by the scheduled power interruption scheduled from February 15-20, 2021.




Notice of Scheduled Power Interruption

From February 15-20, 2021

Date and Time

Affected Areas

Purpose

February 15, 2021

Monday

9:00 AM to 5:00 PM

Sitio Ampasit, Wangal, La Trinidad
  • Extension of Primary lines
  • Installation of 3-37.5kVa Buyback transformers
Part of Purok 3 and 4, East Gibraltar and Upper Gibraltar, Baguio
  • Relocation of Primary pole inside private property
Parts of Lualhati compound (Near Barangay Hall) in Baguio City
  • Extension of Primary lines
  • Installation of 3-37.5kVa Buyback transformers
Marlboro Country, Lamut, Beckel, La Trinidad
  • Upgrading of primary lines from Vee-phase to Three phase

February 16, 2021

Tuesday

9:00 AM to 5:00 PM

Parts of Upper Pinget, Baguio City
  • Relocation of Secondary pole
Parts of Avelino St., Rainbow Hills Subdivision, Central and Lower Fairview, Baguio City
  • Relocation of primary pole affected by on-going construction.
  • Replacement of rotten primary pole

February 17, 2021

Wednesday

9:00AM to 5:00PM

– Parts of Atok: Guiweng, Parts of Abiang, Sayangan, Patapat, Topdac, Englandad Paoay

– Whole of Bakun (Except Kayapa and Lamew)

– Parts of Kabayan: Batan

– Parts of Buguias: Natubleng

– Parts of Kibungan: Palina and major parts of Madaymen

  • Correction of low sagging primary lines
  • Reconfiguration of Primary structure.
Parts of Tebteb, Balili, La Trinidad
  • Replacement and relocation of rotten secondary pole
Parts of lower Heartwell and Lumbag, Ampucao, Itogon.
  • Replacement and reconductoring of secondary lines
February 18, 2021

Thursday

9:00AM to 5:00PM 

La Trinidad: Bineng, Poblacion LT (Buyagan, Windy Hill, CCDC, San Jose, La Trinidad Central School, Valley Bread, Gayasi) 
  • Relocation of primary poles affected by road widening projects

February 19, 2021

Friday

9:00AM to 5:00PM

Baguio City: Parts of Zigzag, Camp 7

Tuba: Whole of Camp 6, Camp 4, Camp 3, Camp 1, Tabaan Sur

  • Relocation of primary pole affected by DPWH project
  • Relocation of Secondary pole affected by on-going construction
Whole of Pias, Camp 7, Baguio City
  • Correction of Leaning Primary pole
  • Correction of Low Voltage
  • Reconductoring of secondary lines from 2/0 to 4/0.
February 20, 2021

Saturday

9:00 AM – 5:00 PM

Baguio City: Parts of Imelda Marcos Barangay (Including Pucay village and justice village), Sto.Rosario Valley, SLU-SVP Housing (Bakakeng Old Site), Bakakeng Norte/Sur (Richview Subdivision, Green Summerville Subdivision, Bakakeng Norte), Bakakeng Central (whole of Marcos Highway), Balacbac, Sto.Tomas Proper, Sto. Tomas School Area, Dontogan.

Tuba: Poblacion TB (including Cabuyao and Poblacion Proper), Taloy Sur, Taloy Norte, Tabaan Norte

  • Relocation of primary and secondary poles affected by DPWH Projects
  • Uprating of Communal distribution transformer from 25kVA to 75kVA.

BENECO Power Interruption Schedule for February 15-20, 2021 (images)

 

BENECO Power Interruption Schedule Feb 15-20, 2021

 

BENECO Power Interruption Schedule Feb 15-20, 2021










BENECO Power Interruption Schedule Feb 15-20, 2021





BENECO Power Interruption Schedule Feb 15-20, 2021





Cable & Communication Companies

In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.

Also, all consumers are advised to always consider all lines energized because power may be restored earlier than the scheduled time.





For other questions and concerns:

For more information and concerns, contact BENECO at any of these numbers:

  • LANDLINE:637-4400 local 605 to 607
  • SMART: 09088657202
  • GLOBE:09175921698

Source: BENECO