Uncategorized

BENECO and NGCP Power Interruption Schedule for August 31 to September 5, 2020




Today, August 28, 2020, the Benguet Electric Cooperative, Inc. (BENECO) and the National Grid Corporation of the Philippines (NGCP)  has released the schedule of Electric Service Interruption for August 31, 2020 to September 5, 2020 affecting several areas in Baguio City and Benguet.

BENECO and NGCP Power Interruption Schedule from August 31 to September 5, 2020

These are the following areas in Baguio City and Benguet affected by the scheduled power interruption scheduled from August 31 to September 5, 2020.

Date

Time Areas Affected 

Purpose

August 31, 2020

(Monday)

9:00 AM to 5:00 PM Ettong Alapang, La Trinidad Rerouting of Secondary Lines
Parts of Buyagan, Poblacion, La Trinidad (near Buyagan Elementary School) Relocation of Pole and Rerouting of Secondary Line
September 1, 2020

(Tuesday)

9:00 AM to 5:00 PM Suello Village, Baguio City -Extension of Primary Lines

-Installation of Buyback Transformers

Moldex Residences, Palispis Highway, Baguio City Downrating of Buyback Distribution Transformers
Clean Fuel, and LTWD Pumping, Puguis, La Trinidad Installation of Buyback Distribution Transformers
September 2, 2020

(Wednesday)

9:00 AM – 5:00 PM Parts of Pinewoods Subdivision, Sta. Lucia Baguio City Replacement of 23kV Communal Distribution Transformer to 13.2kV DT
Whole of Spring Subdivision, San Luis Village, Baguio City -Relocation of Primary Pole
Parts of Bomosgao and Poblacion (near Municipal Hall), Tuba -Extension of Primary Lines

-Installation of Buback Transformers

Parts of Boted, Tawang and Upper Tomay Bahong, La Trinidad Extension of Primary and Secondary Line
Sitio Aminit, Bineng, La Trinidad -Replacement of Rotten Pole

-Right of Way Clearing

Parts of Lamut, Beckel, La Trinidad Replacement of Rotten Poles
September 3, 2020

(Thursday)

9:00 AM – 5:00 PM Parts of Alemar’s and Purok 2, Irisan, Baguio City Rerouting of Secondary Lines
St. Joseph Village, Navy base, Baguio City (Polo Field, Callalilly, Sunflower, Morning Glory, Everlasting, Navy Road, Parts of Purok 5 and Purok 7) -Extension of Primary lines

-Installation of 3-25kVA Buyback Transformers

Parts of Pipingew, Lubas, La Trinidad Correction of Secondary Line Clearances
Parts of Gibraltar, Baguio City Massive Clearing
Dungon, Sison, Pangasinan -Load Splitting

-Installation of Buyback Distribution Transformer

Parts of Camp Lolita, Ampucao, Itogon Replacement of Corroded / Rotten Pole
September 4, 2020

(Friday)

9:00 AM to 5:00 PM Parts of Ampusa, Tadiangan, Tuba Reconductoring of Secondary Lines
6:00 AM to 5:00 PM Whole of Tublay (except Tuel and Acop-Winaca)

Whole of Bokod (except Ambuklao and Bobok-Bisal)

Whole of Kapangan

Whole of Kibungan (except Tacadang and Palina)

Whole of Atok

Whole of Kabayan

-Replacement of Rotten Poles

-Relocation of Pole Affected by DPWH Project

Whole of Bakun (except Kayapa)

Whole of Buguias

Whole of Mankayan

Parts of Cervantes, Ilocos Sur

-Relocation of Pole

-Rerouting of Primary Lines

-Replacement f 13.2kV Insulators to 23kV

September 4, 2020

(NGCP)

6:00 AM to 6:30 AM Whole of Tublay (except Tuel and parts of Caponga)

Whole of Bokod (except Ambuklao)

Whole of Kapangan

Whole of Kibungan

Whole of Atok

Whole of Kabayan

-Shifting of Mankayan-Sagada 69kV Line Road (MOPRECO & HEDCOR Sabangan HEP) including BENECO Mankayan Substation from La Trinidad-Lepanto 69kV Line

Note: Isolation of La Trinidad-Mankayan 69kV (Sagada) line 1 Segment which is scheduled for line maintenance.

3:00 PM to 4:00 PM -Shifting of Mankayan-Sagada 69kV Line loads (MOPReCO & HEDCOR Sabangan HEP) including BENECO Mankayan Substation from La Trinidad-Lepanto 69kV Line.

Note: Normalization of La Trinidad-Sagada & La Trinidad Lepanto 69kV Lines.

6:00 AM to 4:00 PM Whole of Bakun

Whole of Buguias

Whole of Mankayan

-Replacement of flashover / damaged porcelain insulators at Tower Nos. 06, 24, 26, 30, 49, 40, 45, 49, 62, 68, 79, 88, 90, 102, 103, 110, 113, & 114 along La Trinidad-Mankayan 69kV (Sagada) Line 1

-Replacement of flashover insulator Phase ABC with Line Lighting  Protection Device (LLPD) at Tower 93 along La Trinidad-Mankayan 69kV (Sagada) Line 1

-Correction of other identified line defects

Simultaneous preparatory work activities of BENECO in connecting with:

-Tapping / Energizing of new BENECO Sinipsip (Gambang – Amgalueyguey) 69kV Line Segment at Tower No. 109 La Trinidad-Sagada 69kV Line

-Energizing of new BENECO Sinipsip 10MVA Substation

September 5, 2020

(Saturday)

9:00 AM to 5:00 PM Pars of South Drive (Poblete, Paterno, Kneedler St.), Happy Hollow and Camp John Hay; Whole of Baguio Country Club -Rerouting of Primary Lines

-Line Clearing

Cable & Communication Companies

In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.

Also, all consumers are advised to always consider all lines energized because power may be restored earlier than the scheduled time.

For other questions and concerns:

For more information and concerns, contact BENECO at any of these numbers:

  • LANDLINE:637-4400 local 605 to 607
  • SMART: 09088657202
  • GLOBE:09175921698

Source: BENECO